Construction of the Tunnel Systems along the combined (rail and traffic) road from Adler to the mountain resort “Alpika - Servis”
According to the project, it’s planned to construct the combined (rail and traffic) road 49 km long.
Six Tunnel Systems are planned to be constructed along this combined road, including:
- 6 railway tunnels with the total length of 10 425 m,
- 3 traffic tunnel with the total length of 7 587 m,
- 3 service tunnels with the total length of 9 400 m.
The total length of all the tunnels - 27 412 km.
Taking into account the lengths of the tunnels, hydrogeological conditions and construction experience in this area, two methods of tunnel construction are panned to be used: roadheaders and TBMs.
Tunnel Systems:
Download
The information brochure "Tunnel construction along the road Adler - Krasnaya Polyana" can be downloaded in pdf format (19 pages | 5.67 ÌB).
Chronicle of events: 2009
 |
At the beginning of November, excavation of the railway tunnel 4 which is part of the combined (rail and traffic) road from Adler to Alpika Servis started from south portal. Construction is being performed by “Caucasian Tunnel Construction Company” Ltd. The one-track tunnel is 450 meters long. Its excavation is being carried out using «Mitsui Miike» roadheaders and drill and blast method. |
 |
In late September – early October 2009, construction of the railway tunnels of the Tunnel Systems 3 and 6 that are part of the combined (rail and traffic) road from Adler to Alpika-Servis started. Excavation of the railway tunnel 3 began with construction of a launching chamber for the Lovat RM 394DS TBM Ø 10,2 m using benching method. The TBM assembly started in October 2009.Construction of the railway tunnel 6 is being carried out from south portal using mining excavator. The railway tunnel 6 is the only double – track tunnel along this road, its width is 12 meters.
|
 |
August 13, the President of the Russian Federation Dmitry Medvedev had a meeting with student divisions on the job site of the Tunnel System 1. Students of these divisions came to Sochi to take part in construction of the Olympic Projects. During one hour, the President of the Russian Federation was discussing different problems of the student divisions with their leaders and was sharing his own experience with them. Also, among participants of this meeting were: the President of "SC Olympstroy" Taymuraz Bolloev, the RF Minister of Sports, Tourism and Youth Policy Vitaly Mutko, the Vice President of JSC "Russian Railways" Oleg Tony, the Head of DKRS – Sochi Evgeny Solntsev and also management representatives of construction companies, who are responsible for construction of the combined rail and traffic road from the city of Adler to the mountain – climatic resort "Alpika-Servis".
|
 |
At the end of July 2009, on the job sites of the Tunnel Systems 1 and 5 located along the combined (rail and traffic) road from Adler to “Alpika – Servis”, construction of the launching chambers was completed and excavation of the service tunnels started using TBMs. The service tunnel 1 (2420 meters long) is being constructed by means of the Lovat RME 232SE TBM, which was already successfully applied for construction of metro in the city of Novosibirsk. The service tunnel 5 is being constructed by means of the new Lovat RME 167SE TBM. Its length is 2800 meters. Construction of these service tunnels is performed by “Tunnel Division 18” Ltd.
|
 |
At the end of June 2009, excavation of the service tunnel 3, which is part of the Tunnel System 3 commenced. The first meters of the service tunnel are being excavated by means of the roadheader Mitsui Miike in order to construct a launching chamber for TBM. Also, excavation works at the jobsite of the Tunnel System 1 started, where railway and traffic tunnels are being excavated by means of roadheaders.
|
 |
May 27, 2009 ceremonial commencement of the Tunnel System 1 excavation took place. The Tunnel System includes 3 tunnels (railway, traffic and service ones).These tunnels are a major part of the 2014 Winter Olympic Games transport infrastructure. They are located on the combined (rail and traffic) road within Adler and the mountain-climatic resort Alpika – Servis. Taking into account the importance of these tunnels and the tight deadlines of their construction, simultaneous excavation of all three tunnels started 1.5 month earlier than it had been scheduled.
More information... |
 |
March 11, 2009 - At the request of Bamtonnelstroy, “Volga Dnepr” Airlines delivered the first shipment of the tunnel mining equipment necessary for construction of transportation infrastructure facilities for the Olympic Games 2014. This oversized cargo with total weight of 94 tons was delivered from Novosibirsk to Adler by An-124-100 Airplane.
|
 |
November 2008, preparatory works started on the territory, allotted for the job site of the Tunnel System 5. According to the design, the
System 5 will include a traffic tunnel, a railway tunnel and a service tunnel. |
 |
September 2008, construction of the approach road to the south portal of the Tunnel System 1 started.
This Tunnel System includes 3 tunnels – a traffic tunnel, a railway tunnel and a service tunnel.
Excavation works are expected to begin in June 2009. |
|